The draw bench is used for draw the pre-processed pipe billet into final product pipe through required passes. The two draw benches were built in 2012 and seldom used after installation.
Composition:
Oil cylinder, host machine(three frame structures), clamping car, pipe billet lifting, finished product carrier pipe, loading and unloading benches, core bar mechanism, main and auxiliary tanks, and electrical control.
300 T draw bench:
Main technical specification:
Max. drawing force: 300 T
Drawing speed: 0~4.5 m/min
Effective length of finished pipe: 1.5~10 m
O.D. of finished pipe drawing: φ60~φ325 mm
Main cylinder model: φ480×φ260×10500 mm
Max. drawing thickness of finished pipe: 30 mm
System stations: 2 sets
System working pressure: 25 MPa
Max. oil pressure: 31.5 MPa
Main motor power: 75×3 KW
Equipment dimension: 1.7×1.5×50 m
Equipment weight: 120 t
200 T draw bench:
Main technical specification:
Max. drawing force: 200 T
Drawing speed: 0~4.5 m/min
Effective length of finished pipe: 1.5~12 m
O.D. of finished pipe drawing: φ50~φ299 mm
Main cylinder model:φ430×φ260×13500 mm
Max. drawing thickness of finished pipe: 25 mm
System stations: 2 sets
System working pressure: 25 MPa
Max. oil pressure: 31.5 MPa
Main motor power: 55×3 KW
Equipment dimension: 1.7×1.5×58 m
Equipment weight: 100 t
Equipment price:
Asking price: Yang.wang@huaye.us